NG Assembly Building a Month Behind Schedule

Construction on the Nunatsiavut Governments (NG) Assembly Building in Hopedale is behind schedule.

Toby Andersen is the Deputy Minister of the NG.

He says the new building was scheduled to be completed by the end of March 2011.

Unfortunately this is not going to happen.

Andersen says having to get the materials and building supplies in on the freight boats has been the problem, like every other year.

He says the structure of the building has been completed, and the contractors are working on the exterior to have it covered-in for the winter season.

Andersen adds the construction is behind schedule by at least six weeks and is now scheduled to be fully constructed by the end of April 2011.